DESIGN CRITERIA AND SPECIFICATIONS

 

FOR

 

PRESSURE SEWERS, FORCE MAINS,

 

GRINDER PUMPS AND APPURTENANCES

 

BOARD OF PUBLIC UTILITIES

 

CITY OF TULLAHOMA, TENNESSEE

  

SPECIFICATIONS NO. TUB S-289, REV. 2

 

­­­­­­­April 1996

 

TABLE OF CONTENTS

 

 

Detailed Specifications

 

Section 1

Pressure Sewers and Force Mains                                                     

Scope of  Work 

Location of Force Mains 

Pipe Fittings for Force Mains

Excavation for Pipeline TrenchesExcavation for Pipeline Trenches

Rock Excavation

Unauthorized Excavation and Over-Breakage

Chert or Crusher-run Stone for Pipe Bedding and Encapsulating

Pipe Laying

Backfilling Pipeline Trenches

Inspection of Lines - During Construction

Pipeline Marking with Metalized Tape and Detection Wire

Testing of Lines

Concrete Kickers, Anchors and/or Encasements

Resilient Seat Gate Valve

Ball Valves

Service Connections

House Service Junction Box

Valve and/or Cleanout Assemblies

Air Release Valves and Pits

Combination Air and Vacuum Valves and Pits

Replacing Streets and Roadways

Remove and/or Replace Concrete Driveways

Removing and Replacing Sidewalks and Paved Ditches

Removing and Replacing Curb and Gutter

Seeding

Highway Crossings (Bored or Jacked)

Bank Erosion

Environmental Statement

Cleanup

 

Section 2

Grinder Pumps and Appurtenances                                                           

 Scope

Standard Simplex Grinder Pump Units

Standard Duplex Grinder Pump Station

Shop Drawings

Warranty

 

Standard Drawings

Standard Installation Details

 

 

 

 

These Specifications give the minimum requirements for installation of pressure sewer lines, force mains and appurtenances in the City of Tullahoma, Tennessee.  Any special construction problems or conditions not covered under these Specifications shall be submitted to the City for approval.

 


The standard drawings are a part of these Specifications and all construction shall conform to the details shown on the drawings.

 


 

 

SECTION 1

 

PRESSURE SEWERS AND FORCE MAINS

 

 

1.    Scope of  Work

 

       The work to be accomplished under this Section consists of the furnishing of all labor, materials, equipment, and services necessary for the construction of low pressure force mains (pumped sewer lines) and the force mains between the central pumping stations and gravity interceptor sewers.

 

       The low pressure sewer system to be constructed will incorporate a number of individual grinder pumps which will pump the sewage generated at the various residential, institutional and commercial establishments through a complete network of low pressure force mains (pumped sewer lines ranging in size from 2-inch to 6-inch).  The wastewater will be discharged directly into gravity collector sewers or may be repumped by conventional sewage pumps located in central pumping stations through separate force mains to gravity interceptor sewers.

 

       Any contractor, developer, or individual planning to install a pressure sewer system in a new or unsewered development must submit detailed plans prepared by a registered Tullahoma Utilities Board in compliance with Tullahoma Utilities Board Standard Specifications and Details and all applicable State requirements to the Tullahoma Utilities Board and the State Department of Environment and Conservation for review and approval.

 

       The grinder pump installations and associated appurtenances are covered under Section 2 “Grinder Pumps and Appurtenances”.

 

2.    Location of Force Mains

 

       The approximate location of the force mains in relation to the limits of rights-of-way, pavement, etc., is shown on the Plans but not guaranteed.  The location shown was chosen to minimize overall project cost with rock excavation, pavement replacement, crushed stone for traffic bound roadway, customer water services, etc., considered.  The final location as constructed may be varied by the contractor with the approval of the Tullahoma Utilities Board provided (1) the proposed location is approved by the Tennessee Department of Transportation, Coffee or Franklin County Highway Department, the City or other agency or legal entity having jurisdiction; and (2) the effect lessens the project cost.  The final location in any event may be varied by necessity due to construction conditions at the direction of the Tullahoma Utilities Board due to requirement of the Tennessee Department of Transportation, Coffee or Franklin County Highway Department, the City or other agency or legal entity having jurisdiction.

 

 

3.    Pipe Fittings for Force Mains

 

a.       General

 

       In all areas where ductile iron pipe is not specifically shown, force mains and/or pump lines may be either Class 50 or 51 ductile iron or 200 psi SDR 21 PVC pipe.

 

b.       Ductile Iron Pipe

 

       Pipe shall be centrifugally cast, manufactured in accordance with the ANSI Specification A21.51, of Ductile Cast Iron, Grade 6-42-10, for the required operating pressures as shown on the Plans plus surge allowance of 100 psi, for five feet maximum cover for laying condition “B”.  Each pipe shall be hydrostatically tested, before shipment, to a minimum of 500 psi.  Minimum nominal metal thickness shall be:

 

                      Size                        3”             4”             6”             8”             10”

 

                      Class 50                                           0.25            0.27             0.29

 

                      Class 51               0.25            0.26

 

       Joints shall be push-on joint incorporating a single molded rubber ring gasket, Type II, per Federal Specifications WW-P-42lb such as “Fastite”, “Tyton” or “Super Bell-Tite” unless otherwise indicated on the Plans or hereinafter in these Specifications.  Pipe shall be in nominal 16’, 18’, or 20’ lengths.

 

       Pipe shall be furnished tar coated outside and the manufacturer’s standard “Enameline” inside to comply with ANSI Specification A21.4.

 

c.     Cast or Ductile Iron Fittings

 

       All fittings for ductile iron pipe shall be Class 250 mechanical joint cast iron conforming to ANSI Specifications A21.10 and A21.11 or ductile iron conforming to ANSI Specification A21.51, and shall meet the current requirements for the manufacturer’s standards.  Fittings shown on the Plans are intended to convey the general configuration, but the contractor shall furnish all fittings required.

 

       Each fitting shall be certified by the manufacturer to have been tested and to have met the requirements of the governing standard specifications.

 

       All fittings shall be furnished tar coated outside and the manufacturer’s standard “Enameline” inside to comply with ANSI Specification A21.4.

 

 

 

 

 

d.       Polyvinyl Chloride Pipe

 

(1)   Polyvinyl Chloride pipe for force mains shall be made from Type 1, Grade 1 or 2, Polyvinyl Chloride plastic as defined in ASTM Specification D 1784, “Specifications for Rigid Poly (Vinyl Chloride) Compounds.

 

(2)   Physical Properties

 

       The pipe shall conform to Commercial Standard CS-256-63 or ASTM Specification D 2241-80 “Standard Specification for Poly (Vinyl Chloride) (PVC) Plastic Pipe (SDR-PR and Class T)” as it applies to Type I, Grade 1 or 2 Polyvinyl Chloride plastic pipe, SDR 21, water pressure rating of 200 psi at 23° C (72.4° F).

 

(3)   Joints

 

       The joints for pipe 1-1/2 inch in diameter and larger shall be push-on (bell and spigot) joints designed so that the pipe and fittings may be connected on the job without the use of solvent cement or any special equipment.  The push-on joint shall be a single rubber gasket joint designed to be assembled by the positioning of a continuous, molded, rubber ring gasket in an annular recess in the pipe or fitting socket and the forcing of the plain end of the entering pipe into the socket, thereby compressing the gasket radically to the pipe to form a positive seal.  The gasket and the annular recess shall be so designed and shaped that the gasket is locked in place against displacement as the joint is assembled.  Details of the joint design and assembly shall be in accordance with the joint manufacturer’s standard practice.  The joints shall be designed so as to provide for the thermal expansion or contraction experienced with the total temperature change of at least 75° F in each joint per length of pipe.  Joints shall comply with ASTM-D3139.

 

       Joints for fittings shall be of the push-on type as described above unless otherwise noted or directed by the Tullahoma Utilities Board.  Solvent welded type joints shall be allowed on certain types of valves, fittings and piping connections 3-inch and smaller in diameter.  Generally solvent weld joints shall be limited to certain assemblies that can be pre-assembled in the shop and then installed together as a unit in the field.  Examples include the ball valve and clean-out tee that form a unit in a Type A or B valve and clean-out assembly, the ball and check valve assembly that form a unit in a house service junction box, etc.  Solvent cement joints shall be formed by deep-socket couplings integrally cast on the ends of the fittings or valves.  Solvent cement shall conform to ASTM D-2564.

 

(4)   Lubricant

 

       Lubricant furnished for lubricating joints shall be non-toxic, shall not support the growth of bacteria, shall have no deteriorating effects on the gasket or pipe material, and shall not impart color, taste or odor to water.  The lubricant containers shall be labeled with the manufacturer’s name.

 

(5)   Gasket

 

       Gaskets shall meet all applicable requirements of ANSI Standard A21.11 and/or ASTM F477-76.

 

       Gasket dimensions shall be in accordance with the manufacturer’s standard design dimensions and tolerances.  The gasket shall be of such size and shape as to provide an adequate compressive force against the spigot and after assembly to effect a positive seal under all conditions of joint and gasket tolerances.  The trade name or trademark, size, mold number, gasket manufacturer’s mark and year of manufacture shall be molded in the rubber on the back of gaskets.

 

 

       Gaskets shall be vulcanized natural or vulcanized synthetic rubber.  No reclaimed rubber shall be used.  When two hardnesses of rubber are included in a gasket, the soft and hard portions shall be integrally molded and joined in a strong vulcanized bond.  They shall be free of porous areas, foreign material and visible defects.

 

(6)   Pipe Lengths

 

       The pipe shall be furnished in nominal lengths of 20 feet.  The pipe shall be supported at least every 10 feet of its length during all handling, and special care shall be taken to avoid placing undue stress on the pipe during handling, and any actions that may damage the bell or spigot ends of the pipe shall be avoided.

 

 

(7)   Fittings

 

       Fittings to be installed in conjunction with the force mains between the central pumping stations and the treatment facilities (6-inch and larger) shall be cast or ductile iron mechanical joints as described in subparagraph 3.c of this Section.

 

       Fittings to be installed in conjunction with the low pressure force main (pumped sewer lines) shall be of the same material and quality as the pipe and have joints as described in subparagraph 3.d(3) of this Section.  The fittings shall be designed to withstand the same pressures required for the pipe.  The supplier shall be capable of supplying fittings with combinations of spigot (plain) end and bell.

 

       The pipe supplier shall be capable of supplying special pieces for use in connection PVC pipe to cast or ductile iron pipe.

 

(8)   Approval

 

       The pipe and fittings shall be approved by the Division of Water Quality Control, Tennessee Department of Public Health.

 

 

(9)   Marking of Pipe

 

       As a minimum, the pipe shall have the following data applied to each piece:

 

1. Nominal Size

2. Type of Material

3. SDR or Class (color coded)

4. Manufacturer

5. NSF (National Safety Foundation seal of approval)

6. Quality Control Code

 

(10) Testing

 

       The following tests shall be performed by the manufacturer of PVC pipe:

 

       Long-Term Pressure Test (Min.)         1000 hours at 400 psi

       Burst Pressure Short Term (Min.)         640 psi

       Impact (Min.)                     60 ft/lbs at 72° F

                                     16 ft/lbs at   0° F

       Acetone (Min.)                     30 minutes no flaking or

                                        degradation

       Crush (Ring Section)                  100% crush no cracking

       Vacuum Test (Min.)                  22 in/Hg for 24 hrs.  

 

       The manufacturer shall report the results of all tests to the Tullahoma Utilities Board.

 

4.    Excavation for Pipeline Trenches

 

       Unless specifically directed otherwise by the Tullahoma Utilities Board or unless required to uncover or determine the presence of underground obstructions, not more than three hundred (300) feet of trench shall be opened ahead of the pipe laying, and no more than two hundred (200) feet of open ditch shall be left behind the pipe laying.  All barricades, lanterns, watchmen, and other such signs and signals as may be necessary to warn the public to the dangers in connection with open trenches, excavations and other obstructions, shall be provided by and at the expense of the contractor.  All existing traffic control signals, signs or other facilities shall be kept in place and/or in operation by the contractor.  Traffic control signs and construction procedures required by the Tennessee Department of Transportation shall be strictly followed on the portion of the work done on State of Tennessee rights-of-way.

 

       When so required, or when directed by the Tullahoma Utilities Board, only one-half of the street crossings and road crossings shall be excavated before placing temporary bridges over the side excavating for the convenience of the traveling public.  All backfilled ditches shall be maintained in such manner that they will offer no hazard to the passage of traffic.  The convenience of the traveling public and the property owners abutting the improvements shall be taken into consideration.

       All public or private drives shall be promptly backfilled or bridged at the direction of the Tullahoma Utilities Board.  Excavated materials shall be disposed of so as to cause the least interference, and in every case the disposition of excavated materials shall be satisfactory to the Tullahoma Utilities Board.

 

       Trenches shall be opened to a depth so that the top of the pipe shall not be less than two and one-half (2-1/2) feet below the surface of the ground when laid through wooded areas, fields and other such areas outside the pavement or traveled surface of highways and roadways.  The minimum depth of cover shall not be less than three and one-half (3-1/2) feet for pipelines laid within the pavement, traveled surface, or shoulder of any highway and/or roadway.  Any line crossing a State Highway shall have a minimum depth of cover of four (4) feet.  All depths of cover are measured to the top of the pipe.

 

       Trenches shall be of sufficient width to provide free working space on each side of the pipe and to permit proper backfilling around the pipe, but unless specifically authorized by the Tullahoma Utilities Board, trenches shall in no case be excavated or permitted to become wider than one foot six inches (1’ 6”) plus the nominal diameter of the pipe, at the level of the crown of the pipe.

 

       In all areas along State  Highways where the pipeline is being laid in the pavement or in the right-of-way of the road, the Tennessee Department of Highways requires that excavation during each day be limited to the footage of pipe that can be laid and the trench be backfilled, all in accordance with the applicable provisions of this Section of the Detailed Specifications, and so that no open ditch is left overnight in such areas.  The open end of lines in such areas shall be securely plugged when the line is left overnight.

 

       Depth of excavation for footings shall be as shown on the Plans and/or as directed by the Tullahoma Utilities Board to obtain sufficient bearings.  All excavated material not needed for backfilling purposes shall be disposed of in a manner satisfactory to the Tullahoma Utilities Board.

 

       The contractor, at his own expense, shall provide adequate facilities for promptly removing water from all excavations.

 

       The excavation in earth shall be carried to the depth as indicated the Plans and/or directed by the Tullahoma Utilities Board to permit proper bedding of the pipe.

 

       Before laying the pipe, the contractor shall open the trench far enough ahead to reveal obstructions that may necessitate changing the line or grade of the pipeline.

 

       The trench shall be straight and uniform so as to permit laying pipe to lines and grades given by the Tullahoma Utilities Board

 

       The sides of excavations in unstable material shall be supported by substantial sheeting, bracing and shoring or the sides sloped to the angle of repose.  Adequate and proper shoring and bracing shall be solely the responsibility of the contractor.

 

       All excavations shall be accomplished in accordance with applicable safety laws and regulations.

 

5.    Rock Excavation

 

       This includes the excavation of all solid rock, such as limestone or sandstone occurring in mass or ledge formation or such character as to warrant removal by blasting; and it shall also include the removal of boulders equal to or greater than one-half cubic yard in size.

 

       In excavating for pipelines in rock, the excavation shall be carried to a depth of six inches below the invert of the pipe.

 

6.       Unauthorized Excavation and Over-Breakage

 

       Whenever the excavation is carried beyond or below the lines and grades given by the Tullahoma Utilities Board, the contractor, at its own expense, shall refill such excavated space with such material and in such a manner as will insure stability of the line involved including the use of crushed stone or Class “C” concrete.

 

       Over-breakage is that portion of any material displaced or loosened beyond the finished work as planned or authorized by the Tullahoma Utilities Board, including slides.  All over-breakage shall be removed by the contractor and disposed of as directed.

 

7.    Chert or Crusher-run Stone for Pipe Bedding and Encapsulating

 

       Force mains laid in rock are to be encapsulated in a crushed stone envelope and all force mains shall be bedded with crushed stone.  Material for this purpose shall be chert or crusher-run stone meeting the requirements of the Tennessee Department of Transportation, size 67.  A minimum of six inches above the pipe, six inches below, and extending to the ditch line on the sides is required where the pipeline is laid in rock.  Care should be taken to insure that the bedding material has been worked under the pipe and on each side to provide adequate side support.

 

       If unsuitable material is encountered in the trench bottom, the Tullahoma Utilities Board may require additional excavation to insure a firm foundation for the pipe.  In such cases, the trench bottom shall be brought backup to proper grade with bedding material as provided herein.

 

8.    Pipe Laying

 

       The trench shall be excavated to the required depth and width and bell holes and/or jointing holes shall be dug in advance of pipe laying.

 

       The bedding material shall be placed and the bed of each piece of pipe carefully prepared so that each individual piece of pipe has a uniform bearing.  Pipes shall be laid in a straight line and grade without kinks or sags, and shall be laid in a workmanlike manner.

 

       Bell holes and/or jointing holes must be large enough so that the bell or hub will clear the ground and leave ample room for making joint and inspection of joints.

 

       Before each piece of pipe is lowered into the trench, it shall be thoroughly swabbed out to insure its being clean.  Each piece of pipe shall be lowered separately unless special permission is given otherwise by the Tullahoma Utilities Board.

 

       Care shall be taken to prevent injury to the pipe coating, both inside and out.  No piece of pipe or fitting which is known to be defective shall be laid or placed in the lines.  If any defective pipe or fittings are discovered after the pipeline is laid, they shall be removed and replaced with a satisfactory pipe or fitting without additional charge.  In case a length of pipe is cut to fit a line, it shall be so cut as to leave a smooth end at right angles to the  longitudinal axis of the pipe.  Pipe shall be cut only by approved methods as listed in the AWWA Specification covering that type of pipe and lining.

 

       All angles or bends in the pipelines, either vertical or horizontal, shall be satisfactorily braced or anchored against the tendency of movement with a joint harness, concrete or equal anchors to the satisfaction of the Tullahoma Utilities Board.

 

       Open ends of unfinished pipelines shall be securely plugged or closed at the end of each day’s work or when the line is left temporarily at any other time.

 

9.    Backfilling Pipeline Trenches

 

       After the line is bedded and properly laid, crushed stone shall be placed to a level of at least six inches above the top of the pipe where the pipe is laid in rock.  The entire width of the trench shall be filled to this level and compacted adequately to provide uniform side support for the pipeline.

 

       Where the pipe is laid in earth, the backfill from the “haunch” of the pipe to six inches above the top of the pipe may be the earth material excavated from the trench provided that it is free from lumps, frozen material, etc.  Large particles which could damage the pipe shall not be placed in the first 12 inches of backfill above the top of the pipe.  It shall be compacted to a minimum of 90% Standard Proctor Density as determined by ASTM D690.  A minimum of one field density test by an independent testing laboratory per 1,000 feet of line shall be provided and included in the unit price for the pipe.  Additional tests may be ordered by the Tullahoma Utilities Board and any such tests that indicate specified compaction has been achieved shall be paid by the Owner.  If the test indicates inadequate compaction, it and re-test to verify adequate compaction will be paid for the contractor.

 

       In filling the remainder of the trench, the backfill material may be shoveled into the trench without compacting, and heaped over whenever, in the opinion of the Tullahoma Utilities Board, this method of backfilling may be used without inconvenience to the public.

 

       Where street paving or shoulders are to be repaired immediately, the contractor will be required to backfill the entire trench with crushed stone.  Open cut crossings of paved city or county streets will be backfilled with compacted chert or crushed stone.

       Backfill of pipelines laid in the rights-of-way of State highway shall be in accordance with the requirement of the Tennessee Department of Transportation.  Lines laid in the shoulders, paved ramps, driveways within State rights-of-way shall be backfilled with crushed stone.  If paving is to be replaced (except double bituminous), the backfill will stop 11 inches below finish grade to allow for nine inches of binder and two inches of hot mix topping.

 

       Pipe laid in State rights-of-way outside the shoulder may be backfilled with select materials of the same type as the existing natural material or fill in which the trench is dug.  When so required by the Tullahoma Utilities Board, such backfill shall be placed in six-inch layers compacted to 90% Proctor Density.

 

       In areas where the trench is cut into rock or larger broken stone or boulders, and suitable earth backfill is not available, crushed stone backfill may be required to within six inches of the finished grade.  In any trench where the level of excavated rock extends above the level of the top of the pipe, the trench will be backfilled with crushed stone at least six inches above the top of the pipe as a part of the unit price pipe cost.

 

       Before final acceptance, the contractor will be required to level off all trenches where backfill material has been piled up, or to bring the trench up to level of the surrounding street, roadway, or terrain.  The contractor will be required to remove from the streets, roadways, and private property all excess earth or other materials.

 

10.  Inspection of Lines - During Construction

 

       The contractor shall notify the Tullahoma Utilities Board when pipe will be received on the job so that proper arrangements may be made for inspecting the unloading and stringing, as well as inspecting the pipe proper and examining for the manufacturer’s markings for size, class, material code, seal, etc.

 

       Before the contractor backfills any of the lines, they shall be first inspected by the Tullahoma Utilities Board; and the Tullahoma Utilities Board shall give the contractor permission to proceed with the backfilling.  If any joints, pipes, or other workmanship of materials are found to be defective, they shall be removed and replaced by the contractor without any extra compensation.

 

11.  Pipeline Marking with Metalized Tape and Detection Wire

 

       All force mains, pumped sewer lines and house service  lines from  house service junction box to low pressure force main shall be marked by laying a metalized tape in the ditch above the line to allow location by a metal detecting device.  The tape shall be color coded and labeled to identify the type of line and shall be manufactured by Alarmatape, Allen Systems, or equal.  Tape shall be within one foot of finish grade and shall be at least six inches wide.

 

       A detection wire shall be installed with all force mains.  Wire shall be installed with the pipe at the trench bottom and stubbed up at each house service connection, valve and clean-out assembly.  The wire shall be 14 gauge insulated copper wire, commonly called “bell wire”.

 

12.  Testing of Lines

 

       Testing of lines shall comply with the provisions listed below, or similar requirements which will insure equal or better results.

 

a.       Pipelines of whatever material shall be tested at the pressure as shown in the following table at which pressure the allowable leakage shall not exceed the requirements of Section 13 AWWA specification C600-64 as follows:

 

              Pipe Size               Test Pressure       Allowable Leakage per 1,000 Feet

 

              1-1/2 inch               150 psig               0.15 gallons per hour

               2 inch                      150 psig               0.19 gallons per hour

              2-1/2 inch               150 psig               0.23 gallons per hour

               3 inch                      150 psig               0.28 gallons per hour

               4 inch                      150 psig               0.37 gallons per hour

               6 inch                      150 psig               0.55  gallons per hour

               8 inch                      150 psig               0.74 gallons per hour

              10 inch                     150 psig               0.92 gallons per hour

              12 inch                     150 psig               1.10  gallons per hour

 

b.       Pressure shall be measured at low point on section of pipelines.  The contractor shall furnish all gauges, meters, pumps, and other equipment required and shall maintain said equipment in condition for accurate testing as determined by the Tullahoma Utilities Board.

 

c.       Where practical, pipelines shall be tested in lengths between line valves or plugs of no more than 1,500 feet.

 

d.       Where leaks are visible at exposed joints and/or evident on the surface where joints are covered, the pipe shall be rejoined and leakage minimized regardless of total leakage as shown by test.

 

e.       Duration of test shall be not less than two hours where joints are exposed and not less than eight hours where joints are covered.

 

f.     Lines which fail to meet tests shall be repaired and re-tested as necessary until the test requirements are complied with.

 

g.     All pipe, fittings, and other materials found to be defective under the test shall be removed and replaced at the contractor expense.

 

h.       Pipelines should be held under normal operating pressures for at least three days before testing.

 

i.       Generally, pressure testing shall be done after services are laid.  The test shall include the entire service line to the grinder pump installation.

j.     If air relief valves or services are not provided at high points in the lines, a corporation stop shall be provided by the contractor to bleed off air as the line is filled.

 

13.  Concrete Kickers, Anchors and/or Encasements

 

       Concrete kickers, anchors and/or encasement of force mains shall be placed where and as shown on the Plans or as directed by the Tullahoma Utilities Board.  Concrete for anchors, cradle or encasement shall be Class “C” and shall be mixed sufficiently wet to permit it to flow under the pipe to form a continuous bed.  In tamping concrete, care shall be taken not to disturb the grade or line of the pipe or injure the joints.  In pouring thrust blocks on plastic pipe, the pipe will first be wrapped with 4 mil visqueen to prevent adherence of the concrete to the pipe.

 

14.  Resilient Seat Gate Valve

 

       Resilient seat gave valves shall be as manufactured by Mueller company, or equal, suitable for utilization with domestic sewage and working pressures of 200 psi.  The valve shall consist of a cast iron body, a modified wedge disc, resilient rubber seat ring, non-rising stem bronze stem nut cast integrally with valve disc, and O-ring seals mounted above and below the thrust collar.  The resilient seat gate valve shall provide bubble tight shutoff and a full port flow-way.  The valve interior shall be fully protected by a two part thermosetting epoxy coating.  The modified wedge shall be fully supported with the backside traveling along a machined surface in the valve body.  Solid guide lugs on the disc will allow travel within channels cast in the sides of the valve.  The resilient rubber seat ring shall be attached to an annular mounting surface on the front side of the disc with stainless steel screws.

 

       All valves shall be furnished with mechanical joint end connections, unless otherwise shown on the Plans or specified herein.  The end connections furnished shall be suitable for connections to the pipe furnished.

 

       All valves shall have the name or monogram of the manufacturer, the year the valve casting was made, the size of the valve, and the working water pressure cast on the body of the valve.  All valves shall be coated with black asphaltum varnish and shall be touched up in the field as required.

 

       All valves shall be provided with a two-inch square operating nut and shall open by turning to the left (counterclockwise).

 

       Valve boxes shall be cast iron, three piece, screw type with drop cover marked “Sewer”.  They shall be set vertically and properly adjusted so that the cover shall be in the same plane as the finished surface of the ground or street.

 

15.  Ball Valves

 

       Shutoff valves on the pumped sewer lines for sizes three-inch or smaller shall be full ported PVC, Type 1, Grade 1, ball valves with a tee handle actuator.  The valves shall be of the true union type allowing removal of the valve from the line via unions at each end without cutting service line.  Ball valves shall have socket end connections with Teflon seats and Viton “O” rings suitable for service with domestic sewage.  Port opening through ball shall be same size as pipe.  Valves shall be as manufactured by Chemtrol, Hayward Manufacturing Company or equal.

 

16.  Service Connections

 

       The Tullahoma Utilities Board will designate the location of the points on the pumped sewer lines or force mains where fittings are to be installed for service connections.  The contractor shall keep a detailed record of the locations of these fittings as referenced to surface landmarks to allow easy location of each service connection.  Location records shall be submitted to the Resident Inspector as the work progresses.

 

       The pressure service lines from each grinder pump installation to the low pressure force main (pumped sewer line) shall be Class 200, SDR 21, PVC pipe in accordance with the requirements of Paragraph 3.d of this Section of the Specifications.  The pressure service line shall be 1-1/2 inch unless otherwise specified on the Plans and shall be laid to follow the ground profile.  Service lines installed between grinder pumps and house service junction box will not require crushed stone bedding when laid in earth and shall have a minimum cover of 18 inches.  Service lines installed from junction box to pumped sewer line connection point shall be installed in accordance with the requirements of the applicable paragraphs of this Section of the Specifications.  The Tullahoma Utilities Board will designate the routing of the service lines in the field.

 

17.  House Service Junction Box

 

       A house service junction box with shutoff valve and redundant check valve shall be installed in the service line from each grinder pump installation near its intersection with the low pressure force main (pumped sewer line) system.  The exact location of the service junction box shall be determined in the field by the Tullahoma Utilities Board and shall be in non-traffic areas.

 

       The shutoff valve shall be a full ported PVC, Type 1, Grade 1, ball valve with a tee handle actuator.  The valve shall be of the true union type allowing removal of the valve from the line via unions at each end without cutting the service line.  Ball valves shall be 1-1/4 inch in size, with Teflon Seats, socket end connections and Viton “O” rings suitable for service with domestic sewage.  Port opening through ball shall be same size as pipe.  Valves shall be as manufactured by Chemtrol, Hayward Manufacturing Company, or equal.

 

       The redundant check valve shall be 1-1/4 inch of the gravity-operated, flapper type.  The check valve will provide full-ported passageway when open and shall introduce a friction loss of less than six inches of water at maximum rated flow.  Working parts will be made of a 300 series stainless steel and fabric reinforced synthetic elastomer to ensure corrosion resistance, dimensional stability and fatigue strength.  A non-metallic hinge shall be an integral part of the flapper assembly providing maximum degrees of freedom for assured seating at a very low back pressure.  The valve body shall be a high gloss injected molded part made of PVC, Type I-II, with hub and socket compatible with 1-1/4 inch PVC solvent weld system.  Dimensions for hub and socket shall be in accordance with Commercial Standard C5-272-65.

 

       The redundant check valve and ball type shutoff valve shall be housed in a reinforced concrete box as shown on the drawings.  A cover shall be provided which shall have the label “SEWER” stamped into the concrete.

 

18.  Valve and/or Cleanout Assemblies

 

       The various types of valve and/or clean-out assemblies shall be installed at the general locations shown on the Plans.  The exact location of these assemblies shall be determined in the field by the Tullahoma Utilities Board.

 

       Valves 3-inch or less in diameter associated with the valve and/or clean-out assemblies shall be PVC ball valves meeting the requirements of Paragraph 15 of this Section of the specifications.  Valves 4-inch or larger shall be resilient seat gate valves as described in Paragraph 14 of this Section of the Specifications.

 

       Pits shall be as shown on the Plans complete with frame and cover, connecting piping and all accessories as shown on the Plans.

 

19.  Air Release Valves and Pits

 

       Automatic sewage type air release valves and pits shall be installed on the force main at all high points in the lines as shown on the Plans.  The exact location of air release valves shall be determined in the field by the Tullahoma Utilities Board.

 

       Air release valves shall be the short version of Apco Model 400, Crispin 520, or equal.  Valves shall be 2-inch inlet diameter and shall be fitted with proper size of orifices.  The body and cover shall be of cast iron, the trim shall be brass and the float shall be of stainless steel.  The valves shall be suitable for use in lines having a maximum water pressure of 150 psi.  The valve shall be supplied with backwash accessories.

 

       Pits shall be pre-cast or built in place as shown on the Plans, complete with frame and cover, connecting galvanized steel piping, cutoffs, blowoffs and all accessories as shown on the Plans.

 

20.  Combination Air and Vacuum Valves and Pits

 

       Automatic sewage type air and vacuum valves and pits shall be installed on the force main at specific high point locations as shown on the Plans.  The exact location of the combination air and vacuum valves assembly shall be determined in the field by the Tullahoma Utilities Board.

 

       Each combination air and vacuum valve assembly shall consist of an APCO Model 401WA air release valve, or equal.  The air release valve shall have a two-inch inlet diameter and the air and vacuum valve shall have a one-inch minimum inlet.  Each valve shall be fitted with proper size of orifices.  The body and cover of each valve shall be of cast iron, the trim shall be brass and the float shall be of stainless steel.  The valves shall be suitable for use in lines having a maximum water pressure of 150 psi.  Each valve shall be supplied with backwash accessories.

 

       Pits shall be pre-cast or built in place as shown on the Plans, complete with frame and cover, connecting galvanized steel piping, cutoffs, blowoffs, and all accessories as shown on the Plans or as otherwise required for a complete installation.

 

21.  Replacing Streets and Roadways

 

a.       General

 

       The contractor shall replace all streets, alleys and roadways which may be removed, disturbed or damaged in connection with his operation under the contract.  The contractor shall reconstruct same to the original lines and grades and in such manner as to leave all such surfaces in fully as good or better condition than that which existed prior to his operations.  The re-use of materials removed in making excavations will be permitted in the manner described, provided said materials are in good condition and acceptable to the Tullahoma Utilities Board.

 

       All City or County Streets and State Highway crossings shall be backfilled with compacted crushed stone.

 

       Gravel, crushed limestone, bituminous materials, or other materials used in the re-surfacing of streets shall meet the current requirements of the Standard Specifications of the Tennessee Department of Transportation.

 

b.       Removal of Pavement

 

       Where pipelines cross or run within paved surfaces of roadways or driveways, extreme care shall be taken to minimize damage to the paving.  Insofar as possible, paving will be sawed or machine cut to neat, even lines before excavation is started.  Trenches within paved surfaces shall be kept to the smallest width possible consistent with safety requirements.  Where necessary, trench jacks, temporary sheeting or other methods shall be employed to minimize the width of paving cuts and to maintain adequate safety measures.

 

       In addition, the contractor shall make every effort to avoid incidental damage to pavement outside the immediate ditch line by using, insofar as is practical, rubber tired equipment, pads for backhoe leveling jacks, and other such measures that would minimize damage.

 

c.       Traffic-Bound Base Course

 

       Replacement of streets after trenching shall be handled in the following manner:

 

       After the backfill has been compacted to within about three inches of finished grade in accordance with Paragraph 9 of this Section, the contractor shall place approximately four inches of crushed stone as a traffic-bound base course, at the proper elevation to allow settlement, but not in such a way as to prevent traffic from using it.  Crushed stone shall be in accordance with current requirements of the Tennessee Department of Transportation.  Chert, meeting Tennessee Department of Transportation requirements, may be used if approved by the Tullahoma Utilities Board.

 

       The contractor shall maintain the traffic-bound base course by adding crushed stone -- as specified hereinbefore --  in a safe and passable condition for a period of 60 days, or until such time as, in the opinion of the Tullahoma Utilities Board, sufficient settlement has taken place and trenches are ready for final re-surfacing.  Final depth of base is anticipated to be approximately six inches.

 

d.       Subgrade for Final Re-surfacing

 

       The traffic-bound course described above shall comprise the base course for all types of re-surfacing.

 

       When, in the opinion of the Tullahoma Utilities Board, the trench has reached a condition of settlement satisfactory for final re-surfacing, the contractor shall first strip the base course or backfill with crushed stone (size as specified above) to obtain the proper subgrade elevation.  The subgrade shall then be rolled with an approved type roller, or tamped until thoroughly compact and six inches thick.

 

       Any depressions shall be filled with crushed stone or gravel (as specified above) and the process of rolling or tamping continued until the subgrade has a smooth and uniform surface.

 

e.       Portland Cement Concrete Subslab

 

       Where Portland cement concrete pavement subslab is required under bituminous pavement replacement, it shall conform to the existing pavement and/or the Plans (not less than six-inch thickness).  This shall be accomplished with Class “A” concrete.  The subgrade shall be prepared as specified above.

 

f.       Bituminous Sand-Gravel Binder

 

       Where bituminous sand-gravel binder is required as a base under bituminous pavement replacement with State Highway rights-of-way, it shall conform to the current standards of the Tennessee Department of Transportation.  The thickness of the binder course shall not be less than nine inches.  The subgrade shall be prepared as specified above.

 

g.       Asphaltic Concrete Pavement

 

       Where asphaltic concrete pavement is to be replaced, the subgrade shall be prepared as above specified and this subgrade shall comprise the base course upon which the bituminous pavement shall be laid.  The existing pavement shall be neatly cut back approximately one foot outside the trench and the new pavement tied into the existing.

 

       The subgrade or base shall be thoroughly cleaned and broomed and a prime coat of medium tar shall be uniformly applied at a rate of 0.20 to 0.25 gallon per square yard.  Where Portland cement concrete subslab is required, the prime shall be applied to the concrete at a rate of 0.05 gallon per square yard.  The prime shall be applied by a pressure distributor or other approved pressure spray method.

 

       When the prime coat has become tacky, but not dry and hard, a bituminous surfacing consisting of asphaltic concrete shall be placed, spread, finished, and compacted in accordance with the current standards of the Tennessee Department of Transportation.  Compacted thickness of asphaltic concrete pavement replacement shall generally match the thickness of existing paving.

 

       If the existing paving thickness exceeds six inches, the Tullahoma Utilities Board shall be notified for a determination of the required thickness for replacement.  If paving is less than two inches thick, the replacement paving shall be two inches.

 

h.       Bituminous Surfacing (Surface Treatment)

 

       Where bituminous surfacing is to be replaced, as shown on the Plans, or as directed by the Tullahoma Utilities Board, the traffic-bound base shall comprise the subgrade upon which the bituminous surfacing shall be constructed.  After the subgrade or base has been prepared, thoroughly cleaned and broomed, a prime coat of medium tar shall be applied at the rate of 0.30 to 0.35 gallon per square yard.

 

       When the prime coat has become tacky, but not hard, bituminous material (asphalt of the grade directed by the Tullahoma Utilities Board) shall be applied in two applications at the rate of 0.35 to 0.45 gallon per square yard for each application.  The contractor shall apply approximately fifty pounds per square yard to crushed stone ships between the two applications of bituminous material.

 

i.       Untreated Surface

 

       Where the existing surface is untreated crushed stone, the contractor shall replace the surfacing that is disturbed or removed with crushed stone as above specified, to at least the thickness of the existing surface.

 

j.       Portland Cement Concrete Streets

 

       Where Portland Cement concrete pavement must be removed and/or replaced, it shall conform to the existing pavement and/or the Plans and shall be replaced to a thickness equivalent to the existing pavement, but in no case less than six inches.  It shall be accomplished with Class “A” concrete.

 

 

 

22.  Remove and/or Replace Concrete Driveways

 

       Where Portland Cement concrete driveways must be removed and/or replaced, they shall be replaced to a thickness equivalent to the existing pavement, but in no case less than six inches.  It shall be accomplished with Class “A” concrete.

 

23.  Removing and Replacing Sidewalks and Paved Ditches

 

       Whenever sidewalks or paved ditches are removed or disturbed in connection with the construction work, they shall be replaced to the original lines and grades in fully as good or better condition that which existed prior to the contractor’s operations.

 

       After the sub-base has been brought to a satisfactory grade, a 3-inch layer of cinders or crushed stone shall be spread over it and thoroughly tamped. Immediately prior to pouring the concrete, the cinders or stone shall be thoroughly wetted, or the concrete shall be poured on a layer of heavy building paper.

 

       The sidewalk shall consist of 4-1/2 inches of Class “A” concrete, struck of to accurately placed screeds and worked with a wooden float until the mortar appears on the top.  After the surface has been thoroughly floated, it shall be brushed to leave markings of a uniform type similar to the existing walk.  All joints and edges shall be finished with an edging tool.  The allowable variation shall be 1/8 inch to ten feet transversely and longitudinally.

 

       Other types of sidewalks, such as brick, stone, etc., shall be replaced with material removed during the progress of the work, in equally as good condition as that found before work started.

 

24.  Removing and Replacing Curb and Gutter

 

       Where a concrete curb and gutter is damaged or disturbed during the construction, it shall be replaced, using Class ”A” concrete, in fully as good or better condition than which existed prior to the contractor’s operation.

 

25.  Seeding

 

       All disturbed areas shall be left smooth and thickly sown with a mixture of 20% Blue Grass, 30% Italian Rye Grass, 50% Kentucky Fescue *31 and/or such other grasses as are specified by the Engineer.  When the final grading has been completed, the entire area to be seeded shall be fertilized with ammonium nitrate at the rate of five lbs. per 1,000 square feet.  The analysis of the commercial fertilizer shall be determined by soil tests.  After the fertilizer has been distributed, the contractor shall disc or harrow the ground to thoroughly work the fertilizer into the soil.  The seed shall then be sowed in two operations broadcast either by hand or by approved sowing equipment.

 

       The application shall be thirty pounds per acre for each operation.   If the Tullahoma Utilities Board determines to use “hulled” or “unhulled” Bermuda, the application rate shall be seven pounds per acre.  After the seed has been distributed, the contractor shall then lightly cover the seed by use of a drag or other approved device.  All seed shall be certified not more than three percent weed.  The seeded area shall then be covered with straw at the rate of 1-1/4 tons per acre.  The straw mulch shall be tacked with asphalt or held in place by a fabric mat to prevent erosion by water or wind.

 

       Any necessary re-seeding or repairing shall be accomplish